Sacramento County will receive $10.5 million for road rehabilitation projects. Seventeen (17) streets will receive pavement repair with this funding. Roadways selected for treatment were prioritized in the Sacramento County 2008 Transportation Improvement and Program Guide and/or the County Pavement Management Program. The surface treatment provided by this project shall extend the service life of selected roadways by approximately 20 years. Selection of these streets for pavement repair is based on numerous factors including but not limited to: available funding, roadway pavement condition, coordination with other projects, current maintenance needs and maintenance history.

Streets that were selected for stimulus funded repairs are listed below:

Location District Street From To
1 1 44th Street 23rd Avenue 14th Avenue
2 1 Elverta Road 9th Street Rivergreen Drive
3 1 Galbrath Drive Walerga Road Monument Drive
4 1 Monument Drive Don Julio Boulevard Galbrath Drive
5 2 Center Parkway Sacramento City Limits "A" Parkway
6 3 Eastern Avenue Fair Oaks Boulevard Arden Way
7 3 Edison Avenue Howe Avenue Watt Avenue
8 3 Fulton Avenue Munroe street Arden Way
9 4 Greenback Lane Hazel Avenue Chestnut Avenue
10 4 Kenneth Avenue Greenback Lane Central Avenue
11 4 Pershing Avenue Hazel Avenue Filbert avenue
12 4 Winding Way San Juan Avenue Sunrise Boulevard
13 5 Cottonwood Lane Elsie Avenue Stevenson Road
14 5 Huntsman Drive Kiefer Boulevard Rosemont Drive
15 5 Kiefer Boulevard South Watt Avenue Huntsman Drive
16 5 Power Inn Road Elk Grove City Limits Stevenson Road
17 5 Rosemont Drive Kiefer Boulevard Huntsman Road

This project will include the following types of pavement repair work:

  • Base repair: removal of damaged pavement and replacement with new asphalt concrete.
  • Cold planning: controlled milling of pavement surface.
  • Placement of 2-inch conventional or rubberized overlay.
  • Adjusting manholes to grade.
  • Restriping the roadway.
  • Replacing deteriorated portions of curbs, gutters and sidewalks.

Tentative Schedule

Contact Award, August 20098
Work Startup, September 2009
Work Completion, October 2010

Funding

Total project costs are $10.5 million and will be funded by the American Recovery and Reinvestment Act (ARRA). The County’s local share is funded with Measure “A” Sales Tax funds.

Contact Information

Hardeep Sidhu, Project Manager
Senior Civil Engineer
916-875-5490